Construction completed for mobile cabin COVID-19 hospital in Northeast China's Liaoning
People's Daily app
1648648446000
![](https://cdnpdcontent.aikan.pdnews.cn/20220330/e346e1b39c4a4a0a8202b7b3b31d73ff.png)
Round-the-clock construction concluded Tuesday on phase-Ⅰ of a mobile cabin COVID-19 hospital in Shenyang, Northeast China’s Liaoning Province. It took nine days. (Photos: Weibo; compiled by Chen Rui)
![](https://cdnpdcontent.aikan.pdnews.cn/20220330/ae438285be8b4c6fac83152b2ca4329b.jpg)
The 51,000-square-meter project features a 31,000 square-meter room including a 13,000-square-meter warehouse for medical resources and 1,000 beds. The 20,000-square-meter second phase has another 1,000 beds.
![](https://cdnpdcontent.aikan.pdnews.cn/20220330/5c6640cf9a70423b9d0a6c90bb24184f.jpg)
The hospital is split into zero-, half- and full-contamination zones.
![](https://cdnpdcontent.aikan.pdnews.cn/20220330/fb4ce1c7cc8b44b0875b3848ec35184e.jpg)
The second phase is under construction.